A Clear Plan From Quote to Go-Live.
Every implementation follows the same steps, with a dated plan agreed upfront. Here's what happens at each stage, and who is responsible for what.
The Steps
You get a dated version of this plan with your quote.
- 1
Scoping and quote
You: Share how you trade: users, companies, currencies, stock, payroll and any approvals.
ERP Kenya: Send an itemised quote and plan, with every assumption written down for you to confirm.
- 2
Design
You: Confirm the chart of accounts, item structure, approval rules and reports you need.
ERP Kenya: Map your processes onto ERPNext and agree the set-up with you in writing.
- 3
Configuration
You: Answer questions as they come up.
ERP Kenya: Set up the modules, tax templates, workflows, print formats and dashboards.
- 4
Data migration
You: Provide exports from your current system and do a stock count.
ERP Kenya: Clean, import and reconcile opening balances, customers, suppliers and items.
- 5
Testing
You: Run your real transactions in a test copy and sign off.
ERP Kenya: Fix anything that doesn't match how you work.
- 6
Training
You: Make each team available for its sessions.
ERP Kenya: Train each team on its own daily tasks, with short written guides.
- 7
Parallel run
You: Run the last period on both systems, typically payroll.
ERP Kenya: Compare the results and resolve any differences.
- 8
Go-live and support
You: Start trading in ERPNext.
ERP Kenya: Stay close through the first month-end close, then move you onto your support plan.
Why We Recommend a Year-End Go-Live
Going live at the start of your financial year keeps things clean. Payroll starts with the PAYE year, so P9s are not split across two systems. Opening stock comes from the year-end count, and opening balances start at the year boundary.
If your year end is too far away, finance can go live first, with stock and payroll following at the year end. We set out both options in your plan.